SPARO/CSO Plan
Schedule, by subsystem
B = Build, I = Install, T = Test
|
|
1/5 | 1/12 | 1/19 | 1/26 |
2/2 | 2/9 | 2/16 | 2/23 |
3/2 | 3/9 | 3/16 | 3/23 |
3/30 | 4/6 |
Cryostat |
T | T | T | T |
T | | | |
| | | |
| |
Cold Electronics |
B | B | B | B |
B | I | I | T |
T | | | |
| |
Preamps |
B | B | B | B |
T | | | |
| | | |
| |
Data System |
B | B | B | B |
T | | | |
| | | |
| |
Optics |
B | B | B | B |
B | B | B | B |
B | I | T | T |
| |
HWP Control |
| B | B | B |
B | B | B | T |
| | T | T |
| |
System Tests |
| | | |
| | | |
| | | X |
X | |
Packing |
| | | |
| | | |
| | | |
| X |
Schedule, by task
(list of tasks appears below)
|
|
1/5 | 1/12 | 1/19 | 1/26 |
2/2 | 2/9 | 2/16 | 2/23 |
3/2 | 3/9 | 3/16 | 3/23 |
3/30 | 4/6 |
Jessie, David |
1 | 1 | 1 | 1 |
1 | 2,3 | 2,3 | 3,4 |
4,5 | 4,5 | 5 | 6 |
6 | |
Jesse |
1,2,3 | | | |
| | | |
4 | | | |
| |
Bob H. |
1,2 | 1,2 | 1,2,3 | 1,2,3 |
4 | | | |
| | | |
| |
Giles |
1 | 2,3 | 4 | 4 |
4 | 5 | 5 | 6 |
6 | 7 | 7 | 8 |
8 | |
Jim |
1 | 1 | 2 | 2 |
3 | 4 | 4 | 5 |
5 | 6 | | 7 |
| |
Tom |
1 | 1,2 | 2,3 | 2,3 |
2,3 | 2,3 | 2,3 | 2,3 |
3 | 3 | 4 | 4,5 |
5 | |
Bob L. |
| | | 1 |
| | | |
2 | 2 | | |
| |
Jeff |
1 | 1 | 1,2,3 | 3,4 |
3,4 | 3,4 | 3,4 | 3,4 |
3,4,5 | 3,5 | 5 | 5 |
| |
List of Tasks
Jessie/David
- Finish cryostat
- Modify cryostat for signal and thermometry cabling
- Install data analysis software on belmont
- Modify dewar for optics
- Help Develop Plan for Packing Dewar (with Jeff)
- Help with system tests
Jesse
- Finish preamp drawings
- Design and Order 4K PC boards
- Prepare detector arrays for installation
- Install 800 micron concentrators into new holder
Bob H.
- Build A/D box and Nu-bus card
- Assemble preamps
- Install signal and thermometry wires from dewar feed-thrus to
thermometers and JFET boxes
- Assemble JFET boxes
Giles
- Order pressure window, blocking filter, pupil mirror
- Generate numbers for 800 micron concentrators
- Sketch-level design of JFET-boxes
- Sketch-level design of adjustable grid
- Install detectors and electronics into SPARO
- Test SPARO detectors/electronics
- Develop plan for mechanically mounting SPARO at CSO
- Help with system tests
Jim
- Design and build bushing and gear-train for blankoff wheel
- Design and build JFET boxes
- Design and build pupil mirror holder
- Design and build adjustable grid
- Finish hwp assy: gear-train, snout mods, encoder
- Install optics
- Implement plan for mounting dewar at CSO
Tom
- Specify and Order new HWP and field lens
- Develop and test HWP controller
- Develop facility for basic optics testing
- Test optics
- Help with system tests
Bob L.
- Show Giles how to run SPARO software on Yerkes/CSO data system
- Carry out any remaining mods to make SPARO usable at CSO
Jeff
- Build 2.5 inch dia. feedthrus
- Help with drilling of preamp holes in dewar
- Build 800 micron light concentrators
- Build snouts: IVCS, OVCS, 300 K
- Help develop plan for packing and shipping dewar. Implement plan.