|
Cryostat |
| Task | Personnel | Time Frame |
Category | Notes |
| CR1 | Design and Build Dewar Stand |
JJ, DC | July |
Required |
Rings to set down anywhere on either side (?) |
| CR2 | Modify cryostat to allow removal of large-dia. indium
seals |
JJ, DC | July |
Required |
also build fixture for indium press |
| CR3 | Redesign and build Kevlar supports |
DC, JJ | July |
Required |
Include "pins" |
| CR4 | Add He-3 |
JW, DC | July |
Required |
| CR5 | Redesign Optics Snout |
JS | July |
Required |
|
| CR6 | Cold-testing/heating/(disabling?) of External He-3
Components |
PM, DC | July-Aug- Sept-Oct |
Required |
2(1?) kind(s) of gauges, pressure relief valve |
| CR7 | Complete Characterization of Cryostat and Cool Down Cook
Book Development |
DC, JH | July-Aug- Sept-Oct |
Required |
|
| CR8 | New Electrical Feedthrus: Make/procure all parts |
JS | Aug |
Required |
Includes procuring new connectors inside preamps |
| CR9 | Install new shaft for grid adjusters |
DC | Aug |
Required |
also need new Huntington feedthrus |
| CR10 | Build Optics Snout |
JS | Aug |
Required |
|
| CR11 | Order spare 450 micron pressure window |
GN | Aug |
Required |
|
| CR12 | Rebuild pumping port for pumped pot |
JS, GN | Aug |
Required |
KF flange no good at S. Pole. |
| CR13 | Learn how to operate conflat pumpout valve and try it |
JH, DC | Sept |
Required |
KF flange no good at S. Pole. |
| CR14 | Assemble Vellum files of cryostat parts |
DC, JS | Oct |
Required |
|
| CR15 | Spec and Buy He-4 transfer tubes for S. Pole |
JW | Aug |
Required |
Geometry of available room on Viper is unique |
| CR16 | Procure spare for each O-ring in SPARO |
DC, JS | Aug |
Required |
|
| CR17 | Cold-test Optics Snout |
PM, DC | Sept |
Required |
|
| CR18 | Plan mechanical interface to telescope |
TR, GN | Sept |
Required |
| CR19 | Procure external plumbing for pumped pot |
PM, GN | Sept |
Required |
Includes line through cable wrap - must interface with CMU
team on this |
| CR20 | Spec and Purchase vacuum pump for pumped pot |
PM, GN | Sept |
Reqired |
Note: Use the two Alcatels we have (?) |
| CR21 | Develop flowmeter for use at Winterover temps |
DC | Sept |
Required |
Call Sean Casey or test one in dry ice |
| CR22 | Improve Dewar Shipping Protection |
JJ | Oct |
Desirable |
Something betw. He-3 tanks and case; support "other end"
of reservior (?) |
|
Cryostat Monitoring and Control |
| CM1 | Develop software for remote cryo. monitoring |
EL, JH | July-Aug |
Required |
|
| CM2 | Order all connectors & (teflon) cabling for CryoController
functions |
PM, GN | Aug |
Required |
Coord. w/ CMU on connectors & cable length |
| CM3 | Complete Final Electronics/Cabling to run & sample internal
temperature sensors |
PM, RH, GN | Sept |
Required |
Includes testing 4-wire thermometry multiplexer box |
| CM4 | Purchase and test electronic level sensor |
JH | Sept-Oct |
Required |
|
| CM5 | Complete Final Electronics/Cabling to heat charcoal
pumps |
PM, RH, GN | Oct |
Required |
construction done by NU Chem E-shop |
| CM6 | Complete Final Electronics/Cabling to run & sample
He-3 pressure sensors |
PM, RH, GN | Oct |
Required |
construction done by NU Chem E-shop |
|
Cold Electronics |
| CE1 | Test Spare Cold Cable |
GN | July |
Desirable |
- |
| CE2 | Obtain load curves |
GN | July |
Required |
|
| CE3 | Investigate issue of bad JFETs (shorted gates) |
JW, DC, RH, GN, JH | July-Aug |
Required |
JW communicate w/ supplier, DC tests |
| CE4 | Fix bad pixels |
GN, JW, RH, DC, JH | July-Aug- Sept |
Required |
1 broken wire, 1 bad JFET, other (?) |
| CE5 | Reduce/Eliminate Microphonics |
DC, JJ | July-Aug- Sept |
Required |
|
| CE6 | Complete testing of cold electronics |
DC, JH, GN | July-Aug- Sept |
Required |
List of... |
| CE7 | Rework wing support for T-channel |
GN | Aug |
Required |
Involves removing tensioned wires |
| CE9 | Build spare JFET box |
GN, JJ, RH | Sept |
Required |
- |
| CE10 | Remove copper wires from JFET boxes |
RH | Sept |
Desirable |
- |
| CE11 | Develop temperature control system for JFETs |
GN | Sept |
Required |
External wiring may cause noise pickup. Aviod if poss. |
| CE12 | Assemble cold elec. documentation (pinouts, etc.) and put
on Web page |
GN, JH | Sept |
Required |
- |
|
Preamps |
| PR1 | Test all channels for noise, gain |
TR, JH | July-Aug |
Required |
|
| PR2 | Procure battery chargers |
TR | Aug |
Required |
Needed also for data system (Wirth can advise) |
| PR3 | Assemble preamp documentation (pinouts, etc.) and put
on Web page |
TR | Aug |
Required |
- |
| PR4 | Build preamp battery boxes and cables for S. Pole |
RH, PM | Sept |
Required |
Size/length TBD. Cables must be cold-proof |
| PR5 | Implement and Test Preamp heating & temp monitoring |
TR, PM | Sept-Oct |
Required |
|
|
Data System Hardware |
| DH1 | Test/Debug SPARO Data System |
GN, JW, RH, JH | Aug |
Required |
Tom's email... |
| DH2 | Build data system battery boxes and cables for S. Pole |
RH, PM | Aug |
Required |
Location/length TBD. Cables must be cold-proof |
| DH3 | Procure optical fibers for S. Pole & spares |
RH | Aug |
Required |
Length determined by Viper expt. Must be cold-proof. |
| DH4 | Temperature monitoring for data system |
PM, GN | Aug |
Required |
CMU system may do this for their box |
| DH5 | Assemble data system documentation (pinouts, etc.)
and put on Web page |
JW, RH | Aug |
Required |
- |
| DH6 | Add gain control capability |
RH, JW, GN | Aug-Sept |
Required |
Requires adding optical isolators |
| DH7 | Build spare Viper data system enclosure/insulator |
GN | Sept |
Required |
Interface with CMU. |
| DH8 | Purchase Disks/Monitors for S. Pole |
PM, GN | Sept-Oct |
Required |
RL is the expert (GN has notes) |
| DH9 | Test/Debug SPARO Data System spares |
PM, GN | Sept-Oct |
Required |
Every component needs to have a spare |
|
Data System Software |
| DS1 | Program Data Computer to interface with telescope |
RL | Sept-Oct |
Required |
|
| DS2 | Test/Debug SPARO Data System Software |
GN | Oct |
Required |
|
| DS3 | Update existing data system software documentation on
Web page |
GN | Oct |
Required |
- |
|
Optics |
| OP1 | A/R coating on all lenses, hwp |
GN | July |
Required |
Procure poly array lens (?) |
| OP2 | Design Optical Bench |
TR | July |
Required |
|
| OP3 | Calculate precise focus |
TR | July |
Desirable |
thermal contraction included |
| OP4 | Optics documentation -> Web page |
TR | July |
Required |
|
| OP5 | New Huntington for Blankoff wheel |
TR | July |
Required |
need turns counter |
| OP6 | Procure new HWP indexer |
JW | July |
Required |
|
| OP7 | Design Grid Adjusters |
JJ, GN | July-Aug |
Required |
|
| OP8 | Order/Install filters for 450 micron operation |
GN | July-Aug- Sept |
Required |
order blocker in July? Start w/ CSO blockers.
Any changes must be tested. |
| OP9 | Order connectors & (teflon) cabling for half-wave
controller |
PM, GN | Aug |
Required |
Coord. w/ CMU on connectors/cable length |
| OP10 | Construct Grid Adjusters |
JJ | Aug |
Required |
|
| OP11 | Build Optical Bench |
TR | Aug |
Required |
|
| OP12 | Rebuild Array Lens Holders |
GN, JJ | Aug |
Desirable |
|
| OP13 | Reinstall 450 micron Cones |
DC | Aug |
Required |
New washer & screw |
| OP14 | Move hold-down screws on mirror further from beam |
GN | Aug |
Desirable |
|
| OP15 | Complete/Install HWP Encoder |
TR, GN | Aug |
Required |
Minor redesign of entire snout/hwp assy. req'd |
| OP16 | Program HWP monitoring via encoder feedback |
EL, GN | Aug |
Required |
|
| OP17 | Perform Optical Tests |
TR | Aug-Sept- Oct |
Required |
List of tests... |
| OP18 | Cold-testing/heating of Huntington motor |
PM, GN | Sept |
Required |
Goddard system had failures of this component |
| OP19 | Test new software/hardware for HWP moves |
TR | Sept |
Required |
Must test for noise too |
| OP20 | Construct cabling for half-wave
controller |
PM, RH, GN | Oct |
Required |
Some construction carried out by NU Chem E-shop |
|
System Testing |
| ST2 | Measure noise with system fully integrated |
GN, DC, TR, JH | Aug-Sept-Oct |
Required |
|
| ST2 | Test remote hwp control |
TR | Oct |
Required |
|
| ST3 | test remote operation of data system |
GN, PM | Oct |
Required |
|
|
Polar Operations Planning |
| PO1 |
Training the Winter-over scientist (GG) |
GN, TR, DC | Aug-Sept |
Required |
Presumably some at NU |
| PO2 | Develop equipment & procedures to permit on
telescope testing at pole |
TR, GN | Sep |
Required |
List of tests... |
| PO3 | Construct equipment to permit on
telescope testing at pole |
JJ | Oct |
Required |
|
| PO4 | Data Analysis Software Development |
DC | Oct |
Desirable |
What is needed(?) |
| PO5 |
Documentation / Cook Book development |
GN | Oct |
Required |
How much is needed? Exclusively on Web(?) |
|
Other Tasks |
| OT1 | Finalize plan for SPARO computer system |
GN, RL | July |
Required |
data system, hwp control, cryo monitor,
heating of SPARO components, Viper systems and status.
Control from dome.
|
| OT2 | Finalize plan for controlling Viper chopper |
GN | Oct |
Required |
Consult with Jeff P. - prob. just need arb. func. gen.
|
| OT1 | Procure new condensing mirror for Viper |
GN | Sept |
Desirable |
Jeff P. will specify - GN will order
|
| OT2 | Develop centralized system for servo-control of heat
to all systems |
GN | Sept-Oct |
Required |
a/d box, preamps, motors, He-3
components, other. (not incl. JFETs). |
| OT3 | Specify and order more crates |
GN | Oct |
Required |
Surplus(?) |